Hi, Can I assume that any penalties and payments as mentioned will be paid for by the new owner and our share of the profits will be reduced to reflect these payments. Thank you
28-06-2022 18:02:34
We already discussed if we come to a final agreement that:
- The penalty of USD 436,000 due to the delay of the project will be paid by the investor(s); (br> - The payment arrears of USD 50,000 before taxes will be paid by the investor(s); (br> We can again get a postponement for the development and operational delivery of the project. The lump sum for a 2-year extension is USD 4,500 and 1 million Egyptian pounds (approximately USD 53,363). These last 2 amounts must be paid in a reasonable amount of time to prevent the project from being confiscated by the TDA. Fines are non-negotiable. this is part of the (pre)negotiations to move forward. If the land is confiscated, we no longer have a negotiating position and the investor(s) no longer have a project to invest in. It is now essential to have a total budget for the investor as soon as possible in order to be able to finish the project. To avoid delays, I have agreed that:
- The investor requests quotes locally in Marsa Alam for the completion of the resort;
- Our Egyptian lawyer used his contacts in Egypt for a quote for the completion of the resort;
- I myself use my contacts for a quote for the completion of the resort.
- The penalty of USD 436,000 due to the delay of the project will be paid by the investor(s); (br> - The payment arrears of USD 50,000 before taxes will be paid by the investor(s); (br> We can again get a postponement for the development and operational delivery of the project. The lump sum for a 2-year extension is USD 4,500 and 1 million Egyptian pounds (approximately USD 53,363). These last 2 amounts must be paid in a reasonable amount of time to prevent the project from being confiscated by the TDA. Fines are non-negotiable. this is part of the (pre)negotiations to move forward. If the land is confiscated, we no longer have a negotiating position and the investor(s) no longer have a project to invest in. It is now essential to have a total budget for the investor as soon as possible in order to be able to finish the project. To avoid delays, I have agreed that:
- The investor requests quotes locally in Marsa Alam for the completion of the resort;
- Our Egyptian lawyer used his contacts in Egypt for a quote for the completion of the resort;
- I myself use my contacts for a quote for the completion of the resort.